Self-build home: Construction
Introduction.
The construction stage is the process of constructing the works described in the design drawings and specifications. At the end of the stage, the self-build home should be ready for occupation, although the contractor may be required to return to the site, even after occupation, to rectify any defects that appear.
Depending on the procurement route that has been adopted, tasks in this stage, may be undertaken by the self builder, the contractor(s), consultants or the kit-house supplier.
Throughout this stage, it may be necessary to procure items outside of the construction contract that will be required to occupy the home, such as; furniture, kitchen equipment, ICT equipment and so on.
Be aware that whilst self-build clients are ‘domestic clients’ for the purposes of the Construction (Design and Management) Regulations, they can attract health and safety duties under Part 4 of the regulations if they control the way in which construction work is carried out. See CDM for self-builders and domestic clients for more information.
- Ensure site induction talks are carried out, explaining key safety issues and site organisation.
- Introduce a signing in and signing out book for all personnel.
- When appropriate, issue notices for each trade contractor to commence work on site along with instructions regarding phasing and sequencing of the work.
- Co-ordinate the preparation of any additional information required by the trade contractors for construction.
- Where there are proposed variations to the agreed works the self builder should give careful consideration to costs that may be incurred and should assess any alternative options.
- Regular inspections should be carried out and progress photos taken. In particular, photograph defective work before any remedial works are carried out and record the date the photos were taken.
- There should be regular construction progress meetings to assess progress against the programme, resolve design issues, inspect samples, and discuss the organisation of the next stage of the construction works.
- It is important to keep all contractors and suppliers informed about the progress of the project so they are able to plan their manufacture and installation works before receiving a notice to commence work. They will have a number of clients to satisfy and are likely to favour those that allow them to maximise their efficiency.
- Visit major supplier’s factories to check work is in progress and products are as ordered.
- Regular payments must be made to contractor(s) in accordance with the requirements of the contract.
- Throughout the project gather any product literature supplied with goods. File these in preparation for creating an operation and maintenance manual.
- Co-ordinate the utility companies to install meters and connect the permanent services.
- As the construction nears completion, agree procedures for inspections, commissioning, and testing building services.
- Ensure contractor(s) rectify any defects that become apparent during commissioning, testing and inspection procedures.
- Arrange for final inspection of the works by the building control inspector (or approved inspector) and arrange for them to issue a building regulations completion certificate.
- If the works (or trade contracts) are complete, certify practical completion. See practical completion for more information.
- Make any payments due.
- Inform insurers of completion.
Featured articles and news
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.